TITLE
Title
ADULT BEHAVIORAL HEALTH CRISIS CENTER BUILDING GMP
end
SPONSOR
Sponsor
Dan Durham (Tari Maynor-Brady)
end
BACKGROUND
Background
Samet Corporation is the construction manager at risk for the Adult Behavioral Health Crisis Center project. The construction was split into two bid packages. An early site work package was competitively bid and the guaranteed maximum price (GMP) for the site work was previously approved on October 17, 2019, by the Board of Commissioners. This work is in progress.
Samet has also competitively bid the second bid package for the building and the remainder of the construction for the Adult Behavioral Health Crisis Center. A total of 41 bid packages were bid. All bids were received by Samet by November 14, 2019. The GMP for this bid package is $11,572,933 as shown on the attached change order. Adding this to the site work GMP of $3,495,955 equals a total construction contract cost of $15,068,888.
The breakdown of the total project cost is as follows:
Design $ 999,962
Geotechnical Services (pre-con) $ 39,880
Pre-Construction Surveying, Insurance, & Fees $ 39,782
Land $ 1,418,164
CM at Risk Pre-Con Services $ 144,252
Site Work GMP $ 3,495,955
Geotechnical Services (site work) $ 33,900
Building GMP $ 11,572,933
Building Commissioning $ 49,800
Permit Fees $ 130,000 estimated
Construction Admin. Reimbursables $ 31,000 estimated
Furniture, Fixtures, and Equipment $ 849,500 estimated
IT & Security $ 1,000,000 estimated
General Project Contingency $ 594,871
TOTAL PROJECT COST $ 20,400,000
Any unused contingency and allowances will be returned to Guilford County. The construction project is expected to be substantially complete by December 31, 2020. The facility will then be outfitted and staffed as project punchlist items are completed. Open...