Guilford County
File #: 2019-417    Version: 1 Name:
Type: New Business Status: Passed
File created: 11/6/2019 In control: Board of Commissioners
On agenda: 11/21/2019 Final action: 11/21/2019
Title: ADULT BEHAVIORAL HEALTH CRISIS CENTER BUILDING GMP
Attachments: 1. Mental Health Replacement - Amend 11-21-19 PENDING.pdf, 2. Executive Summary BP 1 2 Rev 11-20-19, 3. Change Order No. 001
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE

Title

ADULT BEHAVIORAL HEALTH CRISIS CENTER BUILDING GMP

end

 

SPONSOR

Sponsor

Dan Durham (Tari Maynor-Brady)

end

 

BACKGROUND

Background

Samet Corporation is the construction manager at risk for the Adult Behavioral Health Crisis Center project.  The construction was split into two bid packages.  An early site work package was competitively bid and the guaranteed maximum price (GMP) for the site work was previously approved on October 17, 2019, by the Board of Commissioners.  This work is in progress. 

 

Samet has also competitively bid the second bid package for the building and the remainder of the construction for the Adult Behavioral Health Crisis Center.  A total of 41 bid packages were bid.  All bids were received by Samet by November 14, 2019.  The GMP for this bid package is $11,572,933 as shown on the attached change order.  Adding this to the site work GMP of $3,495,955 equals a total construction contract cost of $15,068,888.

 

The breakdown of the total project cost is as follows:

 

Design

  $        999,962

 

Geotechnical Services (pre-con)

  $           39,880

 

Pre-Construction Surveying, Insurance, & Fees

  $           39,782

 

Land

  $     1,418,164

 

CM at Risk Pre-Con Services

  $        144,252

 

Site Work GMP

  $     3,495,955

 

Geotechnical Services (site work)

  $           33,900

 

Building GMP

  $   11,572,933

 

Building Commissioning

  $           49,800

 

Permit Fees

  $        130,000

estimated

Construction Admin. Reimbursables

  $           31,000

estimated

Furniture, Fixtures, and Equipment

  $        849,500

estimated

IT & Security

  $     1,000,000

estimated

General Project Contingency

  $        594,871

 

 

 

 

TOTAL PROJECT COST

  $  20,400,000

 

 

Any unused contingency and allowances will be returned to Guilford County.  The construction project is expected to be substantially complete by December 31, 2020.  The facility will then be outfitted and staffed as project punchlist items are completed.  Opening of the Adult Behavioral Health Crisis Center is expected in March of 2021.

 

The last page of the attached Executive Summary includes a description of the MWBE outreach efforts.  The estimated MWBE participation rate for the entire construction project (site work and building packages) is 38.6% with a breakdown as follows:

 

Asian

 $                    688,000

          4.6%

Black

 $                 1,142,119

          7.6%

Hispanic

 $                 1,372,393

          9.1%

Female

 $                 2,610,906

        17.3%

 

 

 

TOTAL

 $                5,813,418

        38.6%

 

 

 

Total Construction Contract

 $              15,068,888

 

 

The capital project ordinance for the Mental Health Facility Replacement is currently $6,400,000 as previously approved for design services, pre-construction services by the construction manager at risk, land purchase costs, and site work.  The capital project ordinance for the Mental Health Facility will need to be increased by $14,000,000 to a total of $20,400,000 to provide the necessary funding for construction as described above with additional funds coming from state revenues ($7,700,000), appropriated fund balance ($5,500,000); this is the proceeds from the sale of the Bellemeade property, and unallocated bond proceeds from the 2019 bond issuance ($800,000).

end

 

BUDGET IMPACT

Budget Impact

Capital Project Ordinance Amendment

Mental Health Facility Replacement

$7,700,000 Increase in Federal/State Revenues

$5,500,000 Increase in Appropriated Fund Balance

$800,000 Increase in Bond Proceeds (2019 Issuance)

$14,000,000 Increase in Appropriation to Mental Health Facility Replacement

end

 

REQUESTED ACTION

Requested Action

Approve the revision of the contract with Samet Corporation to construct the Adult Behavioral Health Crisis Center and complete all remaining construction for a Guaranteed Maximum Price of $11,572,933 by approving Change Order No. 1 in substantial form; and amend the Mental Health Facility capital project ordinance to increase project funding by $14,000,000 from state revenues ($7,700,000), appropriated county building construction fund balance ($5,500,000); reflecting proceeds from the Bellemeade property, and unallocated bond proceeds ($800,000; 2019 issuance) bringing the ordinance total to $20,400,000 to provide funding for this contract and other necessary project costs.

end