Guilford County
File #: 2016-316    Version: Name:
Type: Miscellaneous Status: Passed
File created: 8/2/2016 In control: Board of Commissioners
On agenda: 10/6/2016 Final action:
Title: GUILFORD COUNTY SCHOOLS CAPITAL PROJECT BUDGET ADJUSTMENT AND APPROVAL OF PUBLIC SCHOOL BUILDING CAPITAL FUND APPLICATION
Attachments: 1. Summary of Corrections - GCS Projects.pdf, 2. Roofing System-wide - Amended 10-06-16 PENDING.pdf, 3. High Point SCALE Site - Amended 10-06-16 PENDING.pdf, 4. PSBCF Application - Roofing 10-6-16.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE
Title
GUILFORD COUNTY SCHOOLS CAPITAL PROJECT BUDGET ADJUSTMENT AND APPROVAL OF PUBLIC SCHOOL BUILDING CAPITAL FUND APPLICATION
end

SPONSOR
Sponsor
Michael Halford
end

BACKGROUND
Background
On May 5, 2016, the Board of Commissioners approved the transfer of local and state Public School Building Capital Funds from the High Point SCALE project to the Roofing System-Wide project to replace roofs at Grimsley High School. While the total transfer amount between these two projects was correct ($254,494), adjustments need to be made to the sources of funds used for the transfer. The correct funding sources should be $190,870 of state Public School Building Capital Funds and $63,624 of funds transferred from the General Fund. The May 5, 2016 project ordinance amendment moved all of the money from state Public Schools Building Capital Funds. All funds are already in existing project ordinances, so no additional County funds are needed to complete the changes.

In addition to approving the project ordinance amendments noted above, the Board is asked to approve the application to release state Public School Building Funds for re-roofing the auditorium and main office area at Grimsley High School. Both the Board of Education and the Board of Commissioners are required to approve the application request. The Chair of the Board of Education signed the approval on September 14, 2016.
end

ORDINANCE
Ordinance
CAPITAL PROJECT ORDINANCE AMENDMENTS
COUNTY BUILDING CONSTRUCTION FUND
SCHOOL CAPITAL OUTLAY




1. PROJECT ORDINANCE FOR ROOFING - SYSTEM-WIDE
BE IT ORDAINED by the Board of County Commissioners for Guilford County, North Carolina that for the following capital project ordinance for Roofing System-wide adopted November 15, 2012; amended June 18, 2015; amended December 3, 2015; and amended May 5, 2016 is hereby amended in accordance with G.S. 159-13.2:

SECTION 1. The following planned expenditure and associated revenue are hereby authori...

Click here for full text