Guilford County voters have approved a total of $2.0 billion in school bond referendums to address school capital needs identified through a comprehensive facilities master plan jointly developed by the Guilford County Board of Education and Guilford County Board of Commissioners.
On September 9, 2025, the Guilford County Schools Board of Education (BOE) approved a Guaranteed Maximum Price (GMP) for Sumner Elementary; resulting in a requested increase in the project ordinance by $59,145,457 for a total project ordinance of $69,215,755.
end
BUDGET IMPACT
Budget Impact
School Capital Outlay Fund
Sumner Elementary
$59,145,457 increase in appropriation to capital project
$59,145,457 increase in Other Revenue (Bond Proceeds)
end
REQUESTED ACTION
Requested Action
Approve request from the Guilford County Board of Education to amend capital project ordinance for Sumner Elementary to increase the project by $59,145,457, funded with an increase in bond proceeds totaling $59,145,457.