File #: 2026-163    Version: 1 Name:
Type: New Business Status: Passed
File created: 2/13/2026 In control: Board of Commissioners
On agenda: 2/19/2026 Final action: 2/19/2026
Title: TRANSCO PIPELINE EASEMENT
Attachments: 1. Access Road Easement Agreement - 183, 2. Additional Line Receipt and Agreement - 183 and 186.1, 3. Additional Line Receipt and Agreement - 183 and 186.1, 4. Triad Park - ALR, 5. Triad Park - TAR
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE
Title
TRANSCO PIPELINE EASEMENT
end

SPONSOR
Sponsor
Victor Isler, County Manager
end

BACKGROUND
Background
Transcontinental Gas Pipe Line Company, LLC (Transco), a subsidiary of Williams, has received a Certificate of Public Convenience and Necessity from the Federal Energy Regulatory Commission (FERC) to construct the Southeast Supply Enhancement Project, which will expand natural gas capacity in the Southeast. In Guilford County, the project includes installation of a new 42-inch “Salem Loop” pipeline collocated within Transco’s existing corridor across Triad Park (Tax Parcel 6896436846), jointly owned by Guilford and Forsyth Counties. This information was shared at the February 5, 2026 Work Session.
The project will utilize existing right-of-way agreements and requires:
1. An Additional Line Receipt and Easement Agreement authorizing construction of the additional pipeline within the existing corridor
2. A Temporary Access Road Easement Agreement for approximately 4.3 acres of temporary construction access within Triad Park
3. A Purchase and Construction Agreement outlining total compensation of $110,000, construction stipulations, restoration obligations, and indemnification provisions
Construction is anticipated to begin in March 2026 and last approximately 90-120 days. The agreements require restoration of impacted park amenities, including walking trails, parking areas, disc golf tee pads, picnic facilities, and roadway access, to their pre-construction condition or better. Environmental oversight will comply with FERC and North Carolina Department of Environmental Quality requirements, including environmental inspection, erosion and sediment control, and post-construction monitoring.
Total compensation for the two tracts within Triad Park is $110,000, which includes payment for additional pipeline rights, limits of disturbance acreage, temporary access, and damages. Compensation will be distributed in accordance with the existing Interl...