Legislation Details

File #: 2023-294    Version: 1 Name:
Type: Budget Amendment Status: Passed
File created: 4/25/2023 In control: Board of Commissioners
On agenda: 5/18/2023 Final action: 5/18/2023
Title: BUDGET AMENDMENT: GUILFORD COUNTY CAPITAL PROJECT CLOSURES AND AMENDMENTS
Attachments: 1. 23.05.18 - Fund 5000 - Amend & Close Five Capital Projects, 2. 23.05.18 - Fund 5000 - Amend Two Capital Projects, 3. 23.05.18 - Fund 5000 - Establish Four Capital Projects
Related files: 2024-341, 2023-439
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE

title

BUDGET AMENDMENT: GUILFORD COUNTY CAPITAL PROJECT CLOSURES AND AMENDMENTS

end

 

SPONSORS

sponsor

Toy Beeninga, Budget & Management Services Director

Eric Hilton, Facilities Director

Don Warn, Finance Director

end

 

BACKGROUND

background

This item conducts three actions:

1)                     Amends and closes five (5) completed capital projects

2)                     Amends two (2) capital projects that are near completion

3)                     Establishes four (4) new capital projects

 

In total, $2,836,285 in existing project remaining funds will fall to fund balance in the County Building Construction Fund and $1,267,000 of these funds will be appropriated. No additional County funds are required. 

 

Amend and Close Capital Projects

Guilford County has completed work on several capital projects and is requesting board authorization to close the following projects:

 

1)                     EMS Maintenance and Logistics Facility.  Adopted in 2013 with a current budget of $14,416,463, actual expenses of $13,737,958, and a remaining balance of $678,505.  Remaining funds will fall to fund balance in the County Building Construction Fund for future appropriation.

 

2)                     Greene Street Center Renovations.  Adopted in 2009 with a current budget of $648,180, actual expenses of $547,789, and a remaining balance of $100,431.  Remaining funds will fall to fund balance in the County Building Construction Fund for future appropriation.

 

3)                     Greensboro Courthouse HVAC.  Adopted in 2017 with a current budget of $1,150,000, actual expenses of $1,122,473, and a remaining balance of $27,527.  Remaining funds will fall to fund balance in the County Building Construction Fund for future appropriation.

 

4)                     High Point Justice Complex HVAC System.  Adopted in 2015 with a current budget of $1,350,000, actual expenses of $1,237,561, and a remaining balance of $112,439.  Remaining funds will fall to fund balance in the County Building Construction Fund for future appropriation.

 

5)                     Independence Parking Deck Repairs.  Adopted in 2016 with a current budget of $600,000, actual expenses of $465,570, and a remaining balance of $134,430.  Remaining funds will fall to fund balance in the County Building Construction Fund for future appropriation.

 

In total, five (5) projects will be amended and closed, and the resulting $1,053,332 in remaining funds will fall to fund balance in the County Building Construction Fund for future appropriation.

 

 

Amend Capital Projects Nearing Completion

Guilford County has nearly completed work on several capital projects and is requesting board authorization to amend the following projects:

 

1)                     Greensboro Courthouse AV Infrastructure Upgrades.  Adopted in 2021 with a current budget of $506,067, actual plus encumbered expenses of $389,623, and a remaining balance of $116,444.  Remaining funds will fall to fund balance in the County Building Construction Fund for future appropriation.

 

2)                     Mental Health Facility Replacement.  Adopted in 2018 with a current budget of $20,800,000, actual plus encumbered expenses of $19,133,491, and a remaining balance of $1,666,509.  Remaining funds will fall to fund balance in the County Building Construction Fund for future appropriation.

 

In total, two (2) projects will be amended, and the resulting $1,782,953 in remaining funds will fall to fund balance in the County Building Construction Fund for future appropriation.

 

 

Establish Four Capital Projects

 

This amendment establishes four new capital projects, to be funded by appropriated fund balance in the County Building Construction Fund.  These projects include:

 

a)                     Detention Center Shower Pods Repair & Renovation.  $400,000 in project expenses, funded by $400,000 in appropriated fund balance.  Work will repair shower floor and wall coatings in the Detention Center shower pods, including epoxy primer, mid coat, and urethane sealer.

 

b)                     DSS Facility Repair & Renovation.  $417,000 in project expenses, funded by $417,000 in appropriated fund balance.  Work will be conducted at Maple Street to improve safety and security at the Maple Street facility, including ADA enhancements, and security upgrades.  Existing work with existing funds is also addressing additional door security needs.  Work will be conducted at Dundas Circle to improve safety and security facility, including fire safety enhancements, structural improvements to improve facility utilization and exterior egress, and security upgrades.

 

c) Juvenile Detention Facility Security Enhancements.  $200,000 in project expenses, funded by $200,000 in appropriated fund balance.  Work will be conducted at the Juvenile Detention Facility to make safety and security upgrades.

 

d) Parks & Recreation Master Plan.  $250,000 in project expenses, funded by $250,000 in appropriated fund balance.  Work will be contracted complete a master plan for Guilford County Parks & Recreation.

end

 

BUDGET IMPACT

budget impact

County Building Construction Fund

 

EMS Maintenance and Logistics Facility (Amend & Close)

$678,505 decrease in appropriation to project

$678,505 decrease in appropriated fund balance

 

Greene Street Center Renovations (Amend & Close)

$100,431 decrease in appropriation to project

$100,431 decrease in appropriated fund balance

 

Greensboro Courthouse HVAC (Amend & Close)

$27,527 decrease in appropriation to project

$27,527 decrease in appropriated fund balance

 

High Point Justice Complex HVAC System (Amend & Close)

$112,439 decrease in appropriation to project

$112,439 decrease in appropriated fund balance

 

Independence Parking Deck Repairs (Amend & Close)

$134,430 decrease in appropriation to project

$134,430 decrease in appropriated fund balance

 

Greensboro Courthouse AV Infrastructure Upgrades (Amend)

$116,444 decrease in appropriation to project

$116,444 decrease in appropriated fund balance

 

Mental Health Facility Replacement (Amend)

$1,666,509 decrease in appropriation to project

$1,666,509 decrease in appropriated fund balance

 

Detention Center Shower Pods Repair & Renovation (Adopt)

$400,000 in appropriation to project

$400,000 in appropriated fund balance

 

DSS Facility Repair & Renovation (Adopt)

$417,000 in appropriation to project

$417,000 in appropriated fund balance

 

Juvenile Detention Facility Security Enhancements (Adopt)

$200,000 in appropriation to project

$200,000 in appropriated fund balance

 

Parks & Recreation Master Plan (Adopt)

$250,000 in appropriation to project

$250,000 in appropriated fund balance

 

NO ADDITIONAL COUNTY FUNDS REQUIRED

end

 

REQUESTED ACTION

requested action

1)                     Amend and close five (5) capital projects as presented.

2)                     Amend two (2) capital projects as presented.

3)                     Establish capital project Detention Center Show Pods Repair & Renovation, with $400,000 in appropriation to project and $400,000 in appropriated fund balance.

4)                     Establish capital project DSS Facility Repair & Renovation, with $417,000 in appropriation to project and $417,000 in appropriated fund balance.

5)  Establish capital project Juvenile Detention Facility Security Enhancements, with $200,000 in appropriation to project and $200,000 in appropriated fund balance.

6)  Establish capital project Parks & Recreation Master Plan, with $250,000 in appropriation to project and $250,000 in appropriated fund balance.

end