Legislation Details

File #: 2026-349    Version: 1 Name:
Type: New Business Status: Passed
File created: 7/29/2026 In control: Board of Commissioners
On agenda: 8/6/2026 Final action: 8/6/2026
Title: GUILFORD COUNTY SCHOOLS (GCS) CAPITAL PROJECT AMENDMENT: ERWIN MONTESSORI SCHOOL
Attachments: 1. GCS Bond Ordinance Request BOCC Erwin 080626, 2. GCS Bond Ordinance Budget Request 26.08.06, 3. Claxton Elementary AMEND-26.08.06, 4. VPA School- AMEND 26.08.06, 5. Erwin Montessori - 26.08.06 AMEND, 6. GCS Sq Ft Cost_Erwin Montessori 7.30.26
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE

Title

GUILFORD COUNTY SCHOOLS (GCS) CAPITAL PROJECT AMENDMENT:  ERWIN MONTESSORI SCHOOL

end

 

SPONSOR

Sponsor

Dr. Whitney Oakley, GCS Superintendent (Dr. Julius Monk)

end

 

BACKGROUND

Background

Guilford County voters approved $2.0 billion in school bond referendums to address school capital needs identified through a comprehensive facilities master plan jointly developed by the Guilford County Board of Education and Guilford County Board of Commissioners.  The County continues to evaluate funding requests with Guilford County Schools through the Joint Capital & Facilities Committee, which meets quarterly to guide the completion of the school bond program.

 

When establishing a project ordinance, the Board of Commissioners takes multiple steps to monitor projects.  For Erwin Montessori, an initial project ordinance was established for design and pre-construction for $8,372,058 on April 15, 2021. A project ordinance amendment was approved on June 18, 2025 for $3,183,556 for early release work including sitework, utility infrastructure, and pre-purchase of long lead materials.  On July 28, 2026 the Board of Education approved a guaranteed maximum price contract for construction totaling $36,867,302.  This information was reviewed by the Joint Capital & Facilities Committee on July 29, 2026.

 

The total project ordinance will total $51,031,620.  The final project cost ended up being $3.3 million higher than initial programmed amounts based on higher site preparation and onsite expenses.  The additional funding will come from savings from Claxton Elementary ($1,186,695) and Peeler-Hampton Elementary ($2,100,960), which were already completed.

 

The school is a magnet school that will serve an estimated 350 students in a 71,361 square foot facility.

 

Erwin School Site

 

Magnet or Standard School

  Magnet

Original School Count (of students served)

  275

Rebuild School Count (of students served)

  350

GCS Student Count (average for elementary)

  448

Comparable Counties Student Count (average for elementary)

  465

15-year student enrollment projection

  350

Design Cost per Square Foot

  $34.38

Onsite Costs

  $10.7M

GCS On-Site (average for elementary)

  $7.8M

Construction Cost per Square Foot

  $408.23

GCS Construction Cost per Sq. Ft (average for elementary)

  $418.55

NC Construction Cost per Sq. Ft (average for elementary)

  $421.62

end

 

BUDGET IMPACT

Budget Impact

School Capital Outlay Fund

Erwin Montessori at Former Archer Elementary Site

$39,476,006 increase in appropriation to capital project

$39,476,006 increase in Other Revenue (Bond Proceeds)

 

Claxton Elementary

$1,186,695 decrease in appropriation to capital project

$1,186,695 decrease in Other Revenue (Bond Proceeds)

 

New Visual & Performing Arts School

$2,100,960 decrease in appropriation to capital project

$2,100,960 decrease in Other Revenue (Bond Proceeds)

end

 

REQUESTED ACTION

Requested Action

Authorize staff to take any and all necessary actions to amend project ordinances associated with the project readjustments or adopt necessary project ordinances.

end