File #: 2024-378    Version: 1 Name:
Type: New Business Status: Passed
File created: 8/15/2024 In control: Board of Commissioners
On agenda: 8/15/2024 Final action: 8/15/2024
Title: GUILFORD COUNTY SCHOOLS (GCS) CAPITAL PROJECT AMENDMENTS - KISER MIDDLE AND CLAXTON ELEMENTARY
Attachments: 1. BOCC Ordinance Request BOE 07232024 New School, 2. Bond Ordinances Kiser & Claxton 08132024, 3. GCS Kiser Middle AMEND-24.08.15, 4. GCS Claxton Elementary AMEND-24.08.15
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE

Title

GUILFORD COUNTY SCHOOLS (GCS) CAPITAL PROJECT AMENDMENTS - KISER MIDDLE AND CLAXTON ELEMENTARY

end

 

SPONSOR

Sponsor

Dr. Whitley Oakley, GCS Superintendent

end

 

BACKGROUND

Background

The Guilford County Board of Education approved two project ordinance amendments for Kiser Middle and Claxton Elementary on July 23, 2024, to fund these projects through occupancy and close-out.

 

Kiser Middle

•                     The Board of County Commissioners (BoCC) approved a project ordinance for Kiser Middle on April 15, 2021 for $55,478,632, based on estimates included in the Guilford County Schools Master Facilities Plan issued in 2019. 

•                     The BoCC approved a budget amendment for Kiser on January 5, 2023, based on guaranteed maximum price (GMP) contract through the construction phase of the project, bringing the total project ordinance to $81,667,391.

•                     This requested increase, totaling $2,349,332, would support off site road and utility improvements ($258,535), security measures ($453,955), and furniture, fixtures, equipment, and technology ($1,636,842).  The revised ordinance amount would total $84,016,723.

 

Claxton Elementary

•                     The Board of County Commissioners approved a project ordinance Claxton Elementary on April 15, 2021 for $31,333,459, based on estimates included in the Guilford County Schools Master Facilities Plan issued in 2019. 

•                     The BoCC approved a budget amendment for Claxton on January 5, 2023, based on guaranteed maximum price (GMP) contract through the construction phase of the project, bringing the total project ordinance to $50,377,090. 

•                     The requested increase, totaling $888,098, would support installing a playground ($539,047), security measures ($125,000), and furniture, fixtures, equipment, and technology ($244,051).  The revised ordinance amount would total $51,265,188.

 

These project amendments will be funded with bond proceeds from the voter approved $1.7 billion school bond referendum.

end

 

BUDGET IMPACT

Budget Impact

School Capital Outlay Fund

Kiser Middle

$2,349,332 increase in appropriation to capital project

$2,349,332 increase in bond proceeds

 

Claxton Elementary

$888,098 increase in appropriation to capital project

$888,098 increase in bond proceeds

end

 

REQUESTED ACTION

Requested Action

Increase revenues and expenses for Kiser Middle from $81,667,391 to $84,016,723, an increase of $2,349,332; and increase revenues and expenses for Claxton Elementary from $50,377,090 to $51,265,188, an increase of $888,098. This is a total increase to the projects of $3,237,430 to be funded through bond proceeds.

end