TITLE
title
ERWIN SCHOOL DEMOLITION CONTRACT AWARD
end
SPONSOR
sponsor
Eric Hilton (Facilities)
end
BACKGROUND
background
The County completed the acquisition of the former Erwin Montessori School property (Erwin) in December of 2023. After reviewing options for the best use of the property the Board instructed the Facilities department to secure pricing to demolish the existing structures and stabilize the site for future development.
Facilities developed a package of specifications that included asbestos abatement, building demolition, rough grading and site stabilization. Purchasing distributed the Request for Proposal specifications for the demolition project on May 22, 2024 and received proposals on June 14, 2024. Eight proposals were received, and seven were deemed responsive by Purchasing.
A team of County staff ranked the proposals based on the criteria of pricing, ability to safely execute the work, availability of contractor resources, proximity to the work site and MWBE participation. After scoring the proposals, DH Griffin was selected as the best contractor to execute the work.
DH Griffin has the experience to properly remediate the asbestos on site and the capability to quickly execute the demolition work in a safe manner. DH Griffin has adequate resources to quickly mobilize and is headquartered in Guilford County. DH Griffin has committed to an MWBE goal of 43% participation.
DH Griffin proposed to execute the scope of work for $524,000. Staff recommends adding a contingency amount of $52,400.00 given the possibility of unforeseen conditions that may be encountered during the project. This is an owner-controlled contingency, and any un-used funds will be returned to the County.
In addition to the demolition work, Duke Energy will be required to relocate a power distribution line that crosses the property. Since the County is requesting the relocation of the line to allow the site to be cleared, the County is responsible for the cost of the relocation. Staff expects the relocation to cost approximately $11,000.
An existing project ordinance was created to purchase and secure the Erwin site. Currently $43,632 remain in the ordinance that can be applied to the Duke Energy costs and the DH Griffin Contract.
end
BUDGET IMPACT
budget impact
County Building Construction Fund
Erwin School Purchase & Upfit
$543,768 increase in appropriation to project
$543,768 increase in appropriated fund balance
end
REQUESTED ACTION
requested action
Approve Erwin School Demolition contract with DH Griffin, in substantial form, in the amount of $576,400.00 for a term of one year beginning on August 9, 2024 and ending August 8, 2025 and amend the Erwin School Purchase and Upfit project ordinance to increase the project ordinance by $543,768 and increase Appropriated Fund Balance by $543,768.